In response to "A pie chart shows work categories. A is work that needs to be done but isn't complete; B is work that needs to be done and is complete -- (edited)" by prayformojo

Yes, 20%. Add A and B to get all work that needs (or needed) to be done. Then 7/34 still needs to be done; 27/34 is done. -- nm